"Farmers resist land acquisition for canal revival project in Tamil Nadu"
LARR Act, 2013
law replacing 1894 Act; mandates SIA, consent thresholds, and enhanced compensation for land acquisition
Social Impact Assessment (SIA)
mandatory study of social costs and benefits before land acquisition under LARR Act
Canal irrigation has been central to Indian agriculture since the colonial era, when the British constructed extensive canal networks to stabilise agrarian revenue and expand cultivation. The Nandan Canal, built in the late 18th century, exemplifies this legacy — originating from the Thurinjalaru River in Tiruvannamalai district, it once served as the lifeline of 120 villages across Tiruvannamalai and Villupuram districts, discharging water into 36 tanks and irrigating approximately 6,500 acres across both districts at its peak. Over decades, neglect, siltation, and encroachment rendered it largely defunct, depriving downstream farmers of a historically reliable water source.
The legal framework governing land acquisition for such infrastructure has undergone a fundamental transformation. The colonial Land Acquisition Act, 1894 gave the state near-absolute power to acquire private land for 'public purpose' with minimal procedural safeguards. Sustained farmer agitations and judicial scrutiny led to the enactment of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013, which replaced the 1894 law. The LARR Act introduced mandatory Social Impact Assessments (SIAs), consent thresholds (80% for private projects, 70% for PPP projects), and enhanced compensation of up to four times the market value in rural areas. Constitutionally, land remains a State List subject under Entry 18 of the Seventh Schedule, and Article 300A guarantees that no person shall be deprived of property except by authority of law.
As the NCERT analysis of large canal projects such as the Indira Gandhi Canal illustrates, irrigation infrastructure carries ecological risks — waterlogging, soil salinity, and disruption of existing land-use patterns — alongside its developmental benefits. These tensions make the design and implementation of canal projects a recurring site of policy contestation.
The Nandan Link Canal project, proposed by Tamil Nadu's Water Resources Department (WRD), seeks to rejuvenate the defunct Nandan Canal by constructing a new main canal and a branch link canal between Sathanur dam and Samudram village near Cheyyar town — a total distance of 28.95 km. The project is divided into two phases: the first phase covers a 12.45 km main canal along the Then Pennaiyar river connecting Sathanur dam to Pachal village; the second phase involves a 16.5 km branch link canal connecting to Samudram lake, which is the confluence of the Aliyar and Thurinjal rivers — tributaries of the Then Pennaiyar river. The new main canal is designed to be approximately 12 metres wide and 1.5 metres deep.
The project's stated rationale is hydrological: to capture surplus rainwater during the Northeast monsoon and channel it through the revived Nandan Canal to recharge groundwater and expand the cultivable area in the region. …
Recently, linking of which of the following rivers was undertaken?
With reference to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013, consider the following statements:
1.The consent of at least 80% of affected families is required for land acquisition for private companies.
2.The consent of at least 70% of affected families is required for Public-Private Partnership projects.
3.Compensation in rural areas is fixed at two times the market value of the land.
Which of the statements given above is/are correct?
Under the Indian Constitution, land acquisition is governed primarily by which of the following?
Consider the following statements about the Social Impact Assessment (SIA) under the LARR Act, 2013:
1.SIA is mandatory for all land acquisitions regardless of the area involved.
2.The SIA must be conducted by an independent multi-disciplinary expert group.
3.The SIA report must be made available to the public before the acquisition notification is issued.
Which of the statements given above is/are correct?